By Utah ADU Builders · Last verified: July 2026 · Sources: Utah Code §§ 10-21-303, 10-21-304, 10-20-909; city building and ADU pages
In Utah, your ADU timeline is mostly decided before construction starts — by the type of unit and your city’s approval steps, not by one universal number. Plan on roughly 3–6 months for an internal basement conversion and 9–18+ months for a detached backyard unit, from first call to move-in. State law puts a 14-business-day clock on the building-permit plan review, but that is not the same as final approval, and it is only one slice of the project.
Best for: homeowners weighing a specific ADU on a specific lot who need a realistic schedule to plan financing, a tenant, or a family move-in. Less useful if: you only want design inspiration — in that case the ranges below are all you need.
An “ADU” (accessory dwelling unit) is a second, self-contained home on the same lot as a single-family house — a basement apartment, a converted garage, an addition, or a standalone backyard cottage.
✓ What we verified for this page
- Utah’s building plan-review timeframe (state law) and how it applies to cities and counties
- Utah’s internal-ADU law and its impact-fee exemption
- Utah’s detached-ADU law taking effect October 1, 2026
- Published permit-review targets and required pre-permit steps for the cities in our table, from each city’s own materials
- City-specific friction that changes the timeline: predevelopment applications, separate land-use/ADU permits, site plan review, owner-occupancy rules, and rental licensing
- Where a city does not publish an ADU-specific review target, we say so and rely on the statewide benchmark rather than invent a number. All cost and total-time figures are planning estimates.
In This Guide
Quick answer: which ADU path tends to move fastest?
| ADU path | Usually faster when… | Main timeline risk |
|---|---|---|
| Internal / basement ADU (built inside the existing home) | The space already exists and egress, ceiling height, and utilities are workable | Egress windows, fire separation, panel capacity, correction cycles |
| Garage conversion | The garage is structurally sound and parking can be replaced | Replacement parking, foundation/slab, fire separation, utilities |
| Attached ADU (an addition sharing a wall) | A simple addition with clean setbacks and nearby utilities | Structural tie-in, design, engineering, inspections |
| Detached ADU (a standalone structure) | Lot size, access, setbacks, and utilities are favorable | Site plan review, utility runs, separate structure, impact fees |
| Prefab / modular ADU | The design is set and the site is ready | City review and site/utility work still control the schedule |