Utah ADU Cost Methodology
By the Utah ADU Builders Editorial Team · Last verified: July 2026
An ADU (accessory dwelling unit) is a self-contained second home on the same lot as a primary residence — a basement apartment, a garage conversion, an attached addition, or a detached backyard cottage.
What we verified for this page
| We checked | Against these sources |
|---|---|
| Utah state ADU law and the internal-ADU impact-fee rule | Utah Property Rights Ombudsman; Utah Code §§ 10-21-303 and 11-36a-202 |
| City and county ADU rules used as examples | Official Salt Lake City, Salt Lake County, Millcreek, Murray, Draper, and Provo pages |
| How pre-approved city plans work | Salt Lake City Building Services (ADU Standard Plans) |
| Cost inputs and ADU-type assumptions | Published Utah builder/vendor pricing and national cost datasets adjusted to Utah, confidence-banded, with unconfirmed items flagged |
| What our estimates exclude and what we never guarantee | Stated plainly throughout this page |
Full source links are at the bottom of the page.
The short version
| Question | Straight answer |
|---|---|
| What is this page? | A plain-English explanation of our Utah ADU cost methodology — how we estimate ADU costs and how sure we are. |
| Is an estimate the same as a quote? | No. A quote needs a defined scope, plans, site facts, and a builder’s review. |
| What moves the number most? | ADU type, existing structure, utilities, site work, city fees, and finish level. |
| Are permits included? | We include them as allowances; actual permit and fee amounts must be verified locally. |
| Are impact fees included? | Internal ADUs built inside an existing home are exempt under Utah law; detached ADUs and new construction may owe local impact, connection, or utility fees. |
| Best next step | Check feasibility for your property before you compare builder bids. |
What a cost estimate from us actually means
A planning estimate exists to save you time and money before you commit — not to replace a contractor’s bid. It helps you avoid chasing a path that’s clearly too expensive, legally tricky, or wrong for your property. The number gets more reliable as more facts about your lot and city get filled in.
The single biggest cause of “why are these numbers so different?” is that people compare three different things:
Unless everyone is quoting the same scope, the numbers won’t match. When we publish a range, we’re aiming at all-in — and we say so.
Here’s the ladder every estimate climbs:
| Stage | What it is |
|---|---|
| Planning range | A rough early range from ADU type and size |
| Feasibility-adjusted estimate | A property-aware estimate once we know your city and constraints |
| Quote-ready scope | A tighter estimate once site details and fees are checked |
| Contractor bid | A real, contractual number from a builder who has reviewed your project |
How we build a Utah ADU cost range
We don’t pull a number from a single source, and we don’t claim a secret database of every Utah project. We work down a source hierarchy — property facts first, official rules second, real local pricing third — then attach a confidence level and flag anything we couldn’t confirm.
| Priority | What we use | How it’s used |
|---|---|---|
| 1 | Your property facts | City, lot, ADU type, rough size, existing structure, photos |
| 2 | Utah state law | Baseline rules for internal and detached ADUs |
| 3 | City / county ordinance | Setbacks, lot minimums, parking, owner occupancy, rental rules |
| 4 | City & utility fee schedules | Permit, plan-review, impact, and connection allowances |
| 5 | Current Utah builder & vendor pricing | Real local construction and unit pricing, aggregated |
| 6 | National cost datasets, adjusted to Utah | Calibration only — never treated as a Utah quote |
| 7 | Editorial judgment | Applied only after the sourced inputs are clear |
Where our cost inputs come from. For construction cost ranges specifically, we synthesize published Utah builder and vendor pricing, national construction-cost datasets (such as the Angi and HomeGuide cost data referenced on our cost guide) adjusted to the Utah market, and — for fees and utilities — official city and utility schedules. The specific builder, vendor, and dataset sources behind our current ranges are listed on our Utah ADU cost guide.
What our estimates include — and what they don’t
A trustworthy estimate separates construction from design, permits, fees, utilities, site work, and contingency — and it’s clear about what it leaves out. The fastest way to mislead a homeowner is to show a low build number and stay quiet about everything that isn’t in it.
| Usually included in our range | Not included until reviewed — or never guaranteed |
|---|---|
| Typical construction scope for the ADU type | ×Furnishings and appliances beyond standard |
| Design & engineering allowance | ×Landscaping beyond basic restoration |
| Permit & plan-review allowance | ×Financing costs and interest |
| Standard finishes (low / mid / high assumption) | ×Property-tax changes |
| A site-work and utility allowance (broad early on) | ×HOA or CC&R approval and restrictions |
| Contingency for unknowns | ×Permit approval — never guaranteed |
| ×Rental income — never guaranteed | |
| ×Property value increase — never guaranteed | |
| ×Final contractor bid pricing |
Check ADU feasibility for your property.
See how these cost factors apply to your specific lot before you go further.
Check ADU feasibility for your property →Why Utah ADU cost ranges are so wide
Two ADUs of the same square footage can cost tens of thousands of dollars apart, because one might reuse an existing basement while the other needs a new foundation, trenching, utility upgrades, and a full build. A wide first range is the honest answer when the expensive unknowns haven’t been checked yet.
The biggest swing factors:
Existing structure vs. new structure. Basement and garage projects lean on what’s already there. Detached ADUs behave like small houses.
Utility route and capacity. A utility hookup — connecting water, sewer, gas, and electrical to the unit — can move a budget fast. Salt Lake City’s own ADU Handbook flags drain grade and slope as a major up-front issue, and a long or complicated sewer trench can add thousands before any walls go up.
Site work and access. Slope, excavation, rocky soil, drainage, and equipment access all matter, and none of them show up in a square-footage estimate.
City fees. Permit and impact fees — one-time charges a city or utility collects to offset a new unit’s demand on roads, parks, water, and sewer — vary widely from city to city.
Finish level. A simple studio over a garage is not the same estimate as a detached two-bedroom with upgraded finishes.
How the estimate changes by ADU type
We don’t estimate a basement conversion, a garage conversion, a prefab unit, and a detached cottage with the same formula. Each has different cost drivers, different approval risks, and a different “biggest unknown.”
| ADU type | Main cost drivers | Early-estimate confidence | Biggest unknown |
|---|---|---|---|
| Internal / basement | Egress, ceiling height, plumbing, HVAC, electrical, fire separation | Medium (with good photos) | Whether the space can legally and safely become a dwelling |
| Garage conversion | Existing slab and walls, insulation, mechanicals, parking replacement | Low–medium | Whether it triggers parking replacement or structural/utility upgrades |
| Attached addition | Foundation, envelope, roof tie-in, utilities, design | Low–medium | How it connects to the existing home and utilities |
| Prefab / modular | Unit price, foundation, delivery and set, hookups, site work, approvals | Medium for the unit; low all-in until the site is known | What the base price leaves out (often city permit fees and hookups) |
| Detached site-built | New foundation, structure, utilities, site work, setbacks, access | Low before a property review | Utility capacity, site work, city rules, and builder scope |
How we handle Utah law, city rules, permits, and fees
Utah state law sets a floor, but it does not make every ADU type, rental use, fee, or detached structure automatically legal on every property. Our method separates what state law guarantees from what your city and lot still decide.
Internal ADUs
Internal ADUs get the strongest treatment under state law. An internal ADU is specifically defined as a unit created within the existing footprint of an owner-occupied, detached single-family home, for long-term rental of 30 consecutive days or longer. Where it qualifies, it is a permitted use in areas zoned primarily for residential use, and it must meet all applicable building, health, and fire codes (Utah Property Rights Ombudsman; Utah Code § 10-21-303).
Importantly, under Utah Code § 11-36a-202, constructing an internal ADU within an existing primary dwelling is exempt from impact fees. An impact fee is a one-time charge a city or utility levies on new construction to fund roads, parks, water, and sewer capacity; skipping it is a real savings. Standard permit, plan-review, inspection, and utility costs still apply — it’s specifically the impact fee that the statute exempts. Cities can still add reasonable conditions like parking requirements, owner-occupancy rules, and rental permits, so “exempt from impact fees” doesn’t mean “no fees at all.”
Detached ADUs
Detached ADUs are a different story. They can trigger impact fees, minimum lot sizes, setbacks (a setback is the required distance a structure must sit from your property lines), owner-occupancy rules (owner occupancy means you live in either the main home or the ADU), parking replacement, and — in some jurisdictions, for example unincorporated Salt Lake County — written confirmation from your water provider before a permit is issued. Detached-ADU rules are still shifting as Utah cities update their ordinances, so city-specific verification is essential.
How different can it be? Here are current detached-ADU lot-size minimums from five Utah jurisdictions:
Examples verified in July 2026 to illustrate how much rules differ — not a statewide standard. Your city’s current rules, lot minimum, and fees are what actually apply.
| City / county | Minimum lot size for a detached ADU | A few local specifics | Source |
|---|---|---|---|
| Salt Lake City | No minimum lot size for an ADU where ADUs are permitted | Detached capped at 1,000 sq ft; 17 ft height (taller only with added setbacks); owner occupancy; recorded covenant. Zoning, setbacks, parking, and permit rules still apply. | SLC Code 21A.40.200 |
| Salt Lake County (unincorporated) | 7,000 sq ft (6,000 in the PC zone) | Written water-provider confirmation required before a permit; concrete slab required (unless above a garage); owner-occupancy affidavit. | Salt Lake County |
| Millcreek | 8,000 sq ft | Detached max 1,000 sq ft; rear yard only; no separate utility meters — all utilities run from the main home. | Millcreek |
| Murray | 10,000 sq ft | Max 20 ft and one story; 10 ft setbacks; capped at 50% of the primary home or 1,000 sq ft; a licensed contractor is required (no owner-builder). | Murray |
| Draper | 12,000 sq ft | One detached ADU per lot; primary home must be owner-occupied; internal ADUs generally allowed on lots larger than 6,000 sq ft. | Draper |
How city fees actually enter the estimate. We read fees from each city’s own schedule rather than guessing, because they diverge sharply — sometimes in opposite directions. In Provo, for example, a detached ADU requires impact fees for utility connections, parks, and emergency services, and must have its own separate utility meter. Nearby Millcreek does the reverse: it prohibits separate ADU meters and requires all utilities to run from the main home. Same state, opposite rules. That’s why we verify fees and utility requirements for your specific city and lot, and keep current fee amounts on our cost guide, where they can be updated as schedules change.
How reliable is your number?
An honest estimate should tell you how much to trust it. A rough planning range and a contractor’s written bid are not the same thing, and you shouldn’t make big decisions on the first when you need the fourth.
| Level | What it is | Inputs behind it | Use it to… |
|---|---|---|---|
| 1 — Planning range | A rough early range | ADU type, rough size, general area | Sanity-check whether an ADU is even in budget |
| 2 — Feasibility-adjusted | A property-aware estimate | Address, city, photos, known constraints | Decide whether to keep going |
| 3 — Quote-ready scope | A tighter, scoped estimate | Site details, plan/spec assumptions, fee checks | Prepare to request serious builder bids |
| 4 — Contractor bid | A real, contractual number | A builder’s review of your scope, plans, and site | Make project, financing, and contract decisions |
How we label uncertainty.
When a figure isn’t nailed down yet, we say so plainly instead of hiding it behind a single number. You’ll see labels like:
- •Planning allowance — a reasonable placeholder we use before your details are known.
- •Property-specific verification required — a cost that depends on your lot, city, or utilities and needs a real review.
- •Not included until reviewed — items, like final fees or utility upgrades, that we deliberately leave out of an early range.
A number without a confidence level is a guess wearing a suit.
See what kind of ADU your property may support.
Find out which confidence level your estimate can realistically reach.
See what kind of ADU your property may support →How often we update these ranges
ADU cost content goes stale quickly, so every number here has a visible verification date and a defined refresh process:
State law: Checked monthly during the legislative session, and at least quarterly otherwise (Utah Legislature, Utah Code, and the Utah Property Rights Ombudsman).
City ordinances and fee schedules: Reviewed quarterly for priority cities and around fiscal-year fee updates, using official city pages and published fee schedules.
Cost ranges: Reviewed quarterly using current Utah builder and vendor input, and calibrated against public labor and material data — which we use for context only, never as a direct Utah ADU quote.
Where we can’t confirm a current detail from an official published source, we say so rather than presenting a guess as a fact.
How to use this before you request estimates
The most useful next step is turning a broad range into a property-specific path. Before you compare builder bids, gather the facts that actually change feasibility and cost:
| Gather this | Why it matters |
|---|---|
| Property address | Sets your city/county rules and fees |
| Photos of the space or backyard | Flags obvious feasibility issues early |
| The ADU type you want | Basement, garage, attached, prefab, or detached |
| Rough size | Scales the scope |
| Utility panel and route info | Flags electrical, sewer, and water risk |
| Basement ceiling height or garage dimensions | Critical for conversions |
| HOA / CC&R documents | Private rules may affect some projects — though for qualifying internal ADUs, Utah law can limit what an association restricts |
| Your goal | Rental, family housing, guests, office, or resale |
| Budget and timeline | Keeps the plan realistic |
Request a Utah ADU feasibility review.
So the bids you gather are for a scope that\u2019s actually right for your lot.
Request a Utah ADU feasibility review →Frequently asked questions
Sources
- Utah Property Rights Ombudsman — Accessory Dwelling Units — propertyrights.utah.gov/find-the-law/legal-topics/adu/
- Utah Code, Title 10, Chapter 21 (municipal ADUs, incl. § 10-21-303) and § 11-36a-202 (impact fees) — le.utah.gov/xcode/
- Salt Lake City — ADU Standard Plans and Building Services — slc.gov/buildingservices/accessory-dwelling-unit-information/
- Salt Lake City Code § 21A.40.200 (Accessory Dwelling Units) — codelibrary.amlegal.com/codes/saltlakecityut/latest/saltlakecity_ut/0-0-0-68737
- Salt Lake County — Accessory Dwelling Units — saltlakecounty.gov/regional-development/planning-transportation/accessory-dwelling-units-adus/
- Millcreek — Accessory Dwelling Units — millcreekut.gov/341/Accessory-Dwelling-Units-ADUs
- Murray — Accessory Dwelling Units — murray.utah.gov/2168/ADUs---Accessory-Dwelling-Units
- Draper — Accessory Dwelling Units — draperutah.gov/business-development/planning-and-development/accessory-dwelling-units-permits/
- Provo — Accessory Dwelling Units — provo.gov/1367/Accessory-Dwelling-Units
Local rules and fees change. The examples above were verified in July 2026 and are provided to illustrate how much ADU rules and costs vary by city — always confirm current requirements for your specific property.
Utah ADU Builders is an independent Utah-focused ADU planning, feasibility, and builder-matching resource — not a city, HOA, law firm, lender, or licensed contractor. Nothing here is legal, financial, or construction advice.